What to do when your website or software project is overdue

An overdue project needs facts before another promise. The first job is to establish what works, what remains and what is preventing a useful outcome.

Denis KondopoulosPrepared 2 November 20262 min read

1. Preserve the agreed position

Collect the brief, proposal, statements of work, approved changes, plans, invoices and relevant decisions. Record what was expected and which assumptions have changed. Keep a factual timeline rather than a collection of accusations.

Secure appropriate access to accounts, source code, hosting and project documentation. If access is missing, record that dependency and resolve it through the agreed channels. Do not make unplanned production changes while responsibility is unclear.

2. Ask for a demonstration against real tasks

Replace “nearly finished” with a list of demonstrable outcomes. Choose representative tasks such as placing an order, processing an exception or completing an approval. Include the less attractive parts: errors, permissions, reporting and handover.

For each task, identify whether it works, needs correction, has not been built or cannot yet be assessed. A set of screens may show design progress without proving that the business process works end to end.

3. Separate four kinds of outstanding work

CategoryDecision needed
Agreed work not deliveredConfirm owner, remaining effort and acceptance
Unclear requirementDefine the expected behaviour before estimating
New or changed requirementApprove, defer or reject through change control
External dependencyObtain the access, data, content or supplier response

Mixing these categories makes delivery conversations less useful. A delayed content decision and a broken integration need different remedies.

4. Agree the smallest useful recovery outcome

Identify the business capability that must work first and what can wait. A phased release may reduce risk, but only if the first phase is genuinely usable and supportable. Do not launch a partial workflow that creates an unmanageable manual burden without acknowledging it.

Ask the supplier to explain the recovery options, assumptions, dependencies and evidence behind the new plan. Assign named decision owners and dates for decisions, not just dates for development tasks.

5. Choose the delivery route

The sensible route may be continuing with the current supplier, adding a specialist, narrowing scope or arranging a controlled handover. A replacement supplier also needs discovery, access and time to understand the existing work. Switching is not a shortcut around those requirements.

If the parties cannot agree what is complete, an independent technical and commercial assessment can establish a clearer baseline. Contractual remedies and legal disputes are separate matters for an appropriately qualified adviser. Keep the immediate recovery conversation focused on evidence and a workable outcome.

Common questions

Should we stop paying immediately?

That depends on your agreement and circumstances. Obtain appropriate advice on contractual questions; a delivery review should establish the facts first.

Can we use completed code with a new developer?

Check the agreed ownership, licences, access and handover arrangements. Do not assume possession of files proves every right or dependency is resolved.

What should the next progress meeting produce?

A demonstrated position, remaining work by category, named blockers and specific decisions needed to proceed.